An indicative estimate of a commercial /
fleet EV charging install and the grant you could claim. Numbers are public UK
ranges — get itemised quotes before you commit.
Indicative only — not a quote, not financial
advice. WCS: up to £350/socket now, £500/socket from 1 Apr 2026, ≤75% of cost, max
40 sockets, scheme ends 31 Mar 2027. Always confirm on
GOV.UK.
It is an indicative range only, using public grant rates and typical UK price bands. Real cost depends on groundworks, DNO supply and site specifics — always get itemised quotes from OZEV-authorised installers.
What is the Workplace Charging Scheme worth?
Up to £350 per socket until 31 March 2026, rising to up to £500 per socket from 1 April 2026, covering up to 75% of total cost, capped at 40 sockets per applicant. The scheme runs until 31 March 2027.
Can I claim more than one grant?
Yes — the Workplace Charging Scheme and the EV Infrastructure Grant are designed to be used together. Your installer applies both.